SWPPP SITE INSPECTION CHECKLIST FOR CONSTRUCTION STORMWATER (FREE PRINTABLE CHECKLIST)
stormwaterplanning.us/checklists/swppp-inspection-checklist/

summary     Free printable SWPPP inspection checklist based on the EPA Construction General Permit: inspection trigger, disturbed areas, perimeter controls, track-out, inlets, basins, stockpiles, washout, dewatering, discharges and corrective actions.

sections
- Inspection trigger and scope
- Disturbed areas and stabilization
- Perimeter and sediment controls
- Exits, track-out and inlets
- Stockpiles, materials and waste
- Dewatering (if occurring)
- Discharge points and receiving waters
- Follow-up

faq
Q: What should a SWPPP inspection include?
A: Under the EPA CGP: all disturbed areas, every stormwater and pollution prevention control, material and equipment areas, stormwater flow paths, dewatering, discharge points and stabilized areas, plus observations of any discharge and identification of maintenance and corrective action needs.
Q: How often are SWPPP inspections required?
A: Under the EPA CGP, at least every 7 calendar days, or every 14 calendar days and within 24 hours of a 0.25-inch rain or qualifying snowmelt. Sites discharging to impaired or high-quality waters inspect every 7 days and after 0.25-inch storms. State permits vary.
Q: Who can perform a SWPPP inspection?
A: A qualified person as defined by the permit. Under the EPA CGP, for coverage on or after February 17, 2023, that means completing EPA's construction inspection course and exam or holding a current valid certification from a program covering the required topics.

note        Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

Courses delivered by HAZWOPER OSHA Training, LLC, an IACET Accredited ProviderDelivered by an IACET Accredited Provider

Free Printable Checklist

SWPPP Site Inspection Checklist for Construction Stormwater

Walk the site with this list on every routine and storm-event inspection. It follows the areas and checks the EPA Construction General Permit requires.

  • Print or check off on screen
  • Nothing is saved
On this page
  1. Inspection trigger and scope
  2. Disturbed areas and stabilization
  3. Perimeter and sediment controls
  4. Exits, track-out and inlets
  5. Stockpiles, materials and waste
  6. Dewatering (if occurring)
  7. Discharge points and receiving waters
  8. Follow-up
  9. FAQ
Project / NPDES ID
Date / time
Inspector (qualified person) and title
Inspection type (routine / storm event / other)
Rainfall (inches, gauge or station)
Weather now

Use this alongside your SWPPP and site map. Under the EPA CGP, the report must be completed within 24 hours of the inspection and signed by the operator's signatory. Nothing you check here is saved. Learn the rules in the inspections lesson.

Inspection trigger and scope

Disturbed areas and stabilization

Perimeter and sediment controls

Exits, track-out and inlets

Stockpiles, materials and waste

Dewatering (if occurring)

Discharge points and receiving waters

Follow-up

Sources and official references

Last reviewed: October 25, 2026 · Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

FAQ

Frequently asked questions

Under the EPA CGP: all disturbed areas, every stormwater and pollution prevention control, material and equipment areas, stormwater flow paths, dewatering, discharge points and stabilized areas, plus observations of any discharge and identification of maintenance and corrective action needs.

Under the EPA CGP, at least every 7 calendar days, or every 14 calendar days and within 24 hours of a 0.25-inch rain or qualifying snowmelt. Sites discharging to impaired or high-quality waters inspect every 7 days and after 0.25-inch storms. State permits vary.

A qualified person as defined by the permit. Under the EPA CGP, for coverage on or after February 17, 2023, that means completing EPA's construction inspection course and exam or holding a current valid certification from a program covering the required topics.

Need Documented Stormwater Training?

QSP Practitioner and SWPPP Preparer courses aligned with the Clean Water Act, NPDES and the Construction General Permit. Certificate of completion. English & Spanish.