STABILIZED CONSTRUCTION ENTRANCE: SPECS, INSTALLATION AND TRACK-OUT CONTROL (FREE GUIDE)
stormwaterplanning.us/guides/stabilized-construction-entrance/

summary     What a stabilized construction entrance (rock construction exit) is, EPA CGP track-out requirements, typical stone and geotextile specs, wheel washes and rumble plates, maintenance, and same-day sediment removal.

sections
- What the EPA Construction General Permit requires
- Typical specifications
- Extra track-out controls
- Maintenance

faq
Q: What is a stabilized construction entrance?
A: A stabilized construction entrance is a pad of coarse aggregate, usually over geotextile, or mats, at a site exit that removes mud from tires before vehicles reach paved roads.
Q: How quickly must track-out be cleaned up?
A: Under the EPA Construction General Permit, sediment tracked onto paved roads, sidewalks or other paved areas must be removed by the end of the same business day, or by the end of the next business day if it occurs on a non-business day.
Q: What size stone is used for a construction entrance?
A: Specifications vary by state, but many manuals call for clean, coarse crushed stone of roughly 2 to 3 inches, several inches thick, over geotextile. Check your state or local BMP manual.
Q: Can you wash mud off the road with a hose?
A: No. The EPA CGP prohibits hosing or sweeping tracked-out sediment into storm drains, drainage features or receiving waters. Remove it by sweeping, shoveling or vacuuming.

note        Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

Courses delivered by HAZWOPER OSHA Training, LLC, an IACET Accredited ProviderDelivered by an IACET Accredited Provider

Free Guide

Stabilized Construction Entrance: Specs, Installation and Track-Out Control

Mud on the street is one of the fastest ways to get a stormwater violation. A properly built and maintained construction exit, plus same-day cleanup, keeps it off the road.

  • 6 min read
  • Updated October 25, 2026
On this page
  1. What the EPA Construction General Permit requires
  2. Typical specifications
  3. Extra track-out controls
  4. Maintenance
  5. FAQ

A stabilized construction entrance (or construction exit) is a stabilized pad where vehicles leave the site, designed to knock mud off tires before they reach a paved road. Tracked-out sediment on streets washes into storm drains with the next rain.

What the EPA Construction General Permit requires

Under EPA's 2022 CGP, operators must minimize sediment track-out:

  • Restrict vehicles to properly designated exit points.
  • Use appropriate stabilization at all points that exit onto paved roads (the permit's examples are aggregate stone over geotextile or non-woven filter fabric, and turf mats).
  • Add track-out controls as necessary so sediment is removed before vehicles exit.
  • Where sediment is tracked onto paved roads, sidewalks or other paved areas, remove it by the end of the same business day, or by the end of the next business day if it occurs on a non-business day, by sweeping, shoveling or vacuuming.
  • Don't hose or sweep tracked-out sediment into storm drains, drainage features or waters.

Typical specifications

State and local BMP manuals set exact specs. Common practice includes:

ItemTypical practice
StoneClean, coarse crushed aggregate (often 2 to 3 inches, or per the state's gradation)
ThicknessSeveral inches deep (commonly at least 6 inches)
LengthLong enough for several tire rotations on the stone (often 50 feet or more)
WidthFull width of the exit, wide enough for the largest vehicles
GeotextileUnder the stone to keep it from sinking into the subgrade
DrainageRunoff from the pad directed to a sediment control, not the street

Extra track-out controls

  • Rumble strips and rattle plates: steel grates that shake mud loose (both named as examples in the CGP).
  • Wheel washing (also a CGP example): with the wash water routed to a sediment trap or basin, never to the street.
  • Construction mats: reusable mats for short-term or tight exits.
  • Street sweeping: scheduled and on-call, especially in wet weather.

Maintenance

  • Top-dress with fresh stone when the voids fill with mud and the pad stops cleaning tires.
  • Keep vehicles from bypassing the exit.
  • Inspect at every SWPPP inspection and after storms, and check the street at the exit daily.
  • Repair washouts and potholes in the pad.

See sediment control BMPs for the full system.

Sources and official references

Last reviewed: October 25, 2026 · Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

FAQ

Frequently asked questions

A stabilized construction entrance is a pad of coarse aggregate, usually over geotextile, or mats, at a site exit that removes mud from tires before vehicles reach paved roads.

Under the EPA Construction General Permit, sediment tracked onto paved roads, sidewalks or other paved areas must be removed by the end of the same business day, or by the end of the next business day if it occurs on a non-business day.

Specifications vary by state, but many manuals call for clean, coarse crushed stone of roughly 2 to 3 inches, several inches thick, over geotextile. Check your state or local BMP manual.

No. The EPA CGP prohibits hosing or sweeping tracked-out sediment into storm drains, drainage features or receiving waters. Remove it by sweeping, shoveling or vacuuming.