STORMWATER AND SWPPP PRACTICE TEST
stormwaterplanning.us/free-training/practice-test/

summary     Free stormwater and SWPPP practice test: 20 random questions from a bank built on the Clean Water Act, NPDES and the EPA Construction General Permit, with instant scoring. Nothing is saved.
format      20 random questions per attempt from a 96-question bank; graded in-browser; nothing saved

question bank
Q: Where does water entering a typical street storm drain go?
A: Usually directly to local streams, rivers, lakes or bays, often without treatment
Q: What pollutant do construction sites typically release in the largest amounts?
A: Sediment
Q: Why is concrete washout water a stormwater concern?
A: It is highly alkaline (high pH) and harmful to aquatic life
Q: Which is an effect of sediment in a stream?
A: Smothering fish spawning beds and carrying attached pollutants
Q: Which type of control keeps soil from being dislodged in the first place?
A: Erosion control, such as mulch, blankets and vegetation
Q: Why is erosion control generally more effective than sediment control?
A: Preventing soil from moving is easier than trying to catch fine particles once they're suspended in runoff
Q: Construction activities that disturb how much land generally need NPDES stormwater permit coverage?
A: 1 acre or more, or less than 1 acre if part of a larger common plan that disturbs 1 acre or more
Q: Which practice addresses runoff that has concentrated and is cutting rills and gullies?
A: Slope breaks, check dams and velocity dissipation
Q: Which section of the Clean Water Act creates the NPDES permit program?
A: Section 402
Q: What does NPDES stand for?
A: National Pollutant Discharge Elimination System
Q: Phase II of EPA's stormwater rules extended construction permit coverage to sites disturbing how much land?
A: 1 to 5 acres
Q: In most states, who issues construction stormwater permits?
A: A state agency authorized by EPA to run the NPDES program
Q: How does a construction site typically obtain coverage under a general permit?
A: By submitting a Notice of Intent (NOI)
Q: When does EPA's 2022 Construction General Permit expire?
A: 11:59 p.m. on February 16, 2027
Q: What is the key compliance document for construction stormwater permits?
A: The Stormwater Pollution Prevention Plan (SWPPP)
Q: Which of these is NOT one of the three main NPDES stormwater programs?
A: Residential lawn watering
Q: A project will disturb 0.6 acres, but it is part of a subdivision that will disturb 12 acres. Does it need coverage?
A: Yes, it's part of a larger common plan of development that will disturb more than one acre
Q: Under the EPA CGP, which parties are operators?
A: The party with control over plans and specifications and the party with day-to-day operational control
Q: Under the EPA CGP, when must the SWPPP be prepared?
A: Before submitting the Notice of Intent
Q: Under the EPA CGP, how far in advance of construction must a new site submit its NOI?
A: At least 14 calendar days before commencing construction activities
Q: When does EPA CGP coverage begin for a new site?
A: 14 calendar days after EPA notifies the operator that it received a complete NOI, unless delayed or denied
Q: Which sites may qualify for the low erosivity waiver?
A: Sites disturbing 1 to less than 5 acres where the rainfall erosivity factor (R) is less than 5 for the construction period
Q: Within how many days must a Notice of Termination be submitted after a termination condition occurs?
A: 30 calendar days
Q: Under the modified 2022 CGP, what must accompany an NOT based on completing construction?
A: Before and after photographs documenting final stabilization
Q: Under the EPA CGP, when must the SWPPP be developed?
A: Before the Notice of Intent is submitted
Q: Which item belongs on the SWPPP site map?
A: Locations of all stormwater controls, stockpiles, washouts and discharge points
Q: Who must be identified in the SWPPP's stormwater team section?
A: The personnel responsible for permit compliance, including those who install and maintain controls, inspect and take corrective actions
Q: Under the EPA CGP, for coverage on or after February 17, 2023, what makes an inspector a "qualified person"?
A: Completing EPA's construction inspection course for the permit and passing the exam, or holding a current valid certification from a program covering the required topics
Q: After a corrective action changes a control described in the SWPPP, how quickly must the SWPPP be modified under the EPA CGP?
A: Within 7 calendar days of completing the work
Q: How long must the SWPPP and related records be kept under the EPA CGP?
A: At least 3 years from when coverage expires or is terminated
Q: Who signs the SWPPP certification?
A: The operator's authorized signatory
Q: Which is an authorized non-stormwater discharge that the SWPPP may need to address?
A: Uncontaminated construction dewatering water discharged per the permit
Q: What is the main purpose of erosion control?
A: Keep soil from being detached and moved in the first place
Q: Why is phasing construction an effective erosion control practice?
A: It limits how much soil is exposed at any one time
Q: Which practice is best suited to a steep slope that needs immediate cover?
A: An erosion control blanket or bonded fiber matrix
Q: How should tracked equipment be run when roughening a slope?
A: Up and down the slope, so cleat marks run across it
Q: Under the EPA CGP, when must stabilization be initiated in an area that will be inactive for 14 or more days?
A: Immediately, meaning no later than the end of the next business day
Q: A site keeps disturbance to 4 acres at a time and discharges to an unimpaired water. How long does it have to complete stabilization after initiating it under the EPA CGP?
A: 14 calendar days
Q: What does a check dam do?
A: Slows flow in a swale or ditch to reduce channel erosion
Q: Why does the EPA CGP require dust control on exposed soil?
A: Wind-blown dust settles into drainage paths and becomes sediment in stormwater
Q: Under the EPA CGP, when must sediment be removed from a perimeter control?
A: Before it accumulates to one-half of the above-ground height of the control
Q: How should the ends of a perimeter control be installed?
A: Extended up slope, for example at 45 degrees, forming a crescent so water can't flow around the ends
Q: Where is silt fence NOT appropriate?
A: Across a ditch or swale carrying concentrated flow
Q: Mud is tracked onto a public street on a Tuesday. When must it be removed under the EPA CGP?
A: By the end of the same business day
Q: Which method of removing track-out is prohibited?
A: Hosing it into a storm drain inlet
Q: What storage must a sediment basin provide under the EPA CGP?
A: Either the runoff from a 2-year, 24-hour storm or 3,600 cubic feet per acre drained
Q: Why should sediment basin outlets withdraw water from the surface?
A: The cleanest water, with the least suspended sediment, is at the surface
Q: A soil stockpile won't be used for three weeks. What does the EPA CGP require?
A: Cover or temporary stabilization, plus a sediment barrier on the downgradient sides
Q: Under the EPA CGP, what must concrete washout water be directed into?
A: A leak-proof container or leak-proof, lined pit designed not to overflow
Q: Why is concrete washout water harmful to waterways?
A: It's highly alkaline (high pH) and carries fine cement particles
Q: Which discharge does the EPA CGP prohibit?
A: Soaps or detergents used in equipment washing
Q: Where should equipment fueling take place?
A: In a designated area away from drainage features and inlets, with spill kits available
Q: Where should a concrete washout be located?
A: As far away as possible from receiving waters, drainage features and storm drain inlets
Q: How should paints, solvents and fertilizers be stored?
A: Under cover or in sheds, in closed, labeled containers with secondary containment for liquids
Q: A hydraulic hose bursts and sprays oil on the ground. What should happen first?
A: Stop the leak and contain and clean up the spill immediately, then report it as required
Q: Where should portable toilets be placed?
A: Away from inlets and drainage features, on level ground, secured against tipping
Q: How does the EPA CGP define dewatering?
A: Draining accumulated stormwater or groundwater from foundations, vaults, trenches and similar points of accumulation
Q: What must dewatering water be routed through before discharge?
A: A sediment control, such as a sediment basin or pumped-water filter bag, designed to prevent visual turbidity
Q: How often must a dewatering discharge be inspected under the EPA CGP?
A: Once per day on which the discharge occurs
Q: What is the turbidity benchmark for dewatering discharges under the 2022 CGP?
A: 50 NTU, based on the weekly average
Q: Where must turbidity samples be collected?
A: At each discharge point, after treatment and before the water leaves the site or enters a drain
Q: The weekly average turbidity exceeds 50 NTU. What is the first step?
A: Immediately take steps to minimize the discharge, including shutting off the dewatering discharge as soon as safely possible
Q: A dewatering discharge leaves a rainbow sheen on the water. What is needed?
A: An oil-water separator or suitable filtration designed to remove oil and grease
Q: Where should a dewatering filter bag be placed?
A: On a flat, stable, erosion-resistant surface, away from steep slopes, with velocity dissipation at the discharge
Q: Under the EPA CGP standard schedules, which is an acceptable inspection frequency?
A: Once every 14 calendar days and within 24 hours of a storm producing 0.25 inches or more of rain
Q: A site discharges to a sediment-impaired stream. What inspection frequency applies to that portion of the site?
A: Once every 7 calendar days and within 24 hours of a 0.25-inch storm
Q: How much snowfall triggers a snowmelt inspection under the 14-day schedule?
A: 3.25 inches or more within a 24-hour period, once it melts and discharges
Q: Within what time must an inspection report be completed under the EPA CGP?
A: 24 hours of completing the inspection
Q: Which area must be inspected?
A: All points of discharge from the site
Q: Areas of the site have completed stabilization. How may inspection frequency change there?
A: Twice in the first month, no more than 14 days apart, then once per month
Q: If you inspect on the 14-day schedule, how do you show a storm triggered an inspection?
A: Record the rain gauge or representative weather station reading in the inspection report
Q: A discharge is happening during the inspection. What must the inspector do?
A: Identify the discharge points and observe and document the discharge's visual quality, such as color, odor, solids, foam and sheen
Q: A silt fence needs sediment removed but is otherwise intact. What is this?
A: Routine maintenance
Q: A section of silt fence was never installed where the SWPPP shows it. What does the CGP require?
A: Corrective action, because a required control was never installed
Q: A corrective action doesn't need a new control or significant repair. What is the deadline?
A: By the close of the next business day
Q: A blown-out sediment basin outlet needs significant repair. What is the deadline?
A: No later than 7 calendar days from discovery, or document why it's infeasible and the schedule
Q: When must a corrective action condition be entered in the log?
A: Within 24 hours of identifying the condition
Q: Under the EPA CGP, when must stabilization be initiated on an area that will be inactive for 14 or more days?
A: Immediately, no later than the end of the next business day
Q: A site has 8 acres disturbed at once. How long does it have to complete stabilization after initiating it?
A: 7 calendar days
Q: What vegetative cover meets final stabilization under the EPA CGP?
A: Uniform, perennial vegetation providing 70% or more of the cover native to local undisturbed areas
Q: How does adding impervious surface typically change runoff?
A: It increases runoff volume and peak flow
Q: What is the main purpose of a dry detention pond?
A: Temporarily store runoff and release it slowly to reduce peak flow
Q: What distinguishes a retention (wet) pond from a detention pond?
A: It maintains a permanent pool of water
Q: Which practice primarily reduces runoff volume?
A: An infiltration basin or bioretention cell
Q: What is low impact development (LID)?
A: Managing rainfall close to where it falls with practices that mimic natural hydrology
Q: Which MS4 control measure addresses permanent stormwater management for new development?
A: Post-construction stormwater management in new development and redevelopment
Q: What is the most common reason permanent stormwater practices fail?
A: Lack of maintenance, such as clogged outlets and sediment-filled ponds
Q: Which practice uses a stone reservoir under a surface that lets water pass through?
A: Permeable pavement
Q: What does MS4 stand for?
A: Municipal separate storm sewer system
Q: How many minimum control measures do small MS4 permits require?
A: Six
Q: Which is one of the six minimum control measures?
A: Illicit discharge detection and elimination
Q: The construction site runoff control measure applies to sites disturbing at least how much land?
A: 1 acre
Q: Which permit does EPA issue for industrial stormwater where it's the permitting authority?
A: The Multi-Sector General Permit (MSGP)
Q: What is a no exposure certification?
A: An exclusion for industrial facilities whose materials and activities aren't exposed to stormwater
Q: Which routine requirement is common under industrial stormwater permits?
A: Quarterly visual assessments of stormwater discharges
Q: Why do cities review construction erosion control plans?
A: Because the MS4 construction runoff control measure requires an ordinance, plan review, inspections and enforcement

Courses delivered by HAZWOPER OSHA Training, LLC, an IACET Accredited ProviderDelivered by an IACET Accredited Provider

Leer en español

Free Practice Test

Stormwater and SWPPP Practice Test

Test what you know about NPDES, permit coverage, SWPPPs, erosion and sediment controls, inspections and stabilization, with an explanation for every answer.

  • 20 random questions per attempt
  • 96-question bank
  • Instant scoring
  • Nothing is saved

This practice test pulls questions from all 12 free lessons. It is a study aid, not an exam for a certificate or a state credential, and your answers are never stored.

Knowledge check

Stormwater practice test: 20 random questions

Each attempt draws 20 questions from the 96-question bank built from our free lessons. Score 80% or higher to pass. Select New random test for a fresh set. Nothing you answer is saved or sent.

Question 1 Where does water entering a typical street storm drain go?
Question 2 What pollutant do construction sites typically release in the largest amounts?
Question 3 Why is concrete washout water a stormwater concern?
Question 4 Which is an effect of sediment in a stream?
Question 5 Which type of control keeps soil from being dislodged in the first place?
Question 6 Why is erosion control generally more effective than sediment control?
Question 7 Construction activities that disturb how much land generally need NPDES stormwater permit coverage?
Question 8 Which practice addresses runoff that has concentrated and is cutting rills and gullies?
Question 9 Which section of the Clean Water Act creates the NPDES permit program?
Question 10 What does NPDES stand for?
Question 11 Phase II of EPA's stormwater rules extended construction permit coverage to sites disturbing how much land?
Question 12 In most states, who issues construction stormwater permits?
Question 13 How does a construction site typically obtain coverage under a general permit?
Question 14 When does EPA's 2022 Construction General Permit expire?
Question 15 What is the key compliance document for construction stormwater permits?
Question 16 Which of these is NOT one of the three main NPDES stormwater programs?
Question 17 A project will disturb 0.6 acres, but it is part of a subdivision that will disturb 12 acres. Does it need coverage?
Question 18 Under the EPA CGP, which parties are operators?
Question 19 Under the EPA CGP, when must the SWPPP be prepared?
Question 20 Under the EPA CGP, how far in advance of construction must a new site submit its NOI?
Question 21 When does EPA CGP coverage begin for a new site?
Question 22 Which sites may qualify for the low erosivity waiver?
Question 23 Within how many days must a Notice of Termination be submitted after a termination condition occurs?
Question 24 Under the modified 2022 CGP, what must accompany an NOT based on completing construction?
Question 25 Under the EPA CGP, when must the SWPPP be developed?
Question 26 Which item belongs on the SWPPP site map?
Question 27 Who must be identified in the SWPPP's stormwater team section?
Question 28 Under the EPA CGP, for coverage on or after February 17, 2023, what makes an inspector a "qualified person"?
Question 29 After a corrective action changes a control described in the SWPPP, how quickly must the SWPPP be modified under the EPA CGP?
Question 30 How long must the SWPPP and related records be kept under the EPA CGP?
Question 31 Who signs the SWPPP certification?
Question 32 Which is an authorized non-stormwater discharge that the SWPPP may need to address?
Question 33 What is the main purpose of erosion control?
Question 34 Why is phasing construction an effective erosion control practice?
Question 35 Which practice is best suited to a steep slope that needs immediate cover?
Question 36 How should tracked equipment be run when roughening a slope?
Question 37 Under the EPA CGP, when must stabilization be initiated in an area that will be inactive for 14 or more days?
Question 38 A site keeps disturbance to 4 acres at a time and discharges to an unimpaired water. How long does it have to complete stabilization after initiating it under the EPA CGP?
Question 39 What does a check dam do?
Question 40 Why does the EPA CGP require dust control on exposed soil?
Question 41 Under the EPA CGP, when must sediment be removed from a perimeter control?
Question 42 How should the ends of a perimeter control be installed?
Question 43 Where is silt fence NOT appropriate?
Question 44 Mud is tracked onto a public street on a Tuesday. When must it be removed under the EPA CGP?
Question 45 Which method of removing track-out is prohibited?
Question 46 What storage must a sediment basin provide under the EPA CGP?
Question 47 Why should sediment basin outlets withdraw water from the surface?
Question 48 A soil stockpile won't be used for three weeks. What does the EPA CGP require?
Question 49 Under the EPA CGP, what must concrete washout water be directed into?
Question 50 Why is concrete washout water harmful to waterways?
Question 51 Which discharge does the EPA CGP prohibit?
Question 52 Where should equipment fueling take place?
Question 53 Where should a concrete washout be located?
Question 54 How should paints, solvents and fertilizers be stored?
Question 55 A hydraulic hose bursts and sprays oil on the ground. What should happen first?
Question 56 Where should portable toilets be placed?
Question 57 How does the EPA CGP define dewatering?
Question 58 What must dewatering water be routed through before discharge?
Question 59 How often must a dewatering discharge be inspected under the EPA CGP?
Question 60 What is the turbidity benchmark for dewatering discharges under the 2022 CGP?
Question 61 Where must turbidity samples be collected?
Question 62 The weekly average turbidity exceeds 50 NTU. What is the first step?
Question 63 A dewatering discharge leaves a rainbow sheen on the water. What is needed?
Question 64 Where should a dewatering filter bag be placed?
Question 65 Under the EPA CGP standard schedules, which is an acceptable inspection frequency?
Question 66 A site discharges to a sediment-impaired stream. What inspection frequency applies to that portion of the site?
Question 67 How much snowfall triggers a snowmelt inspection under the 14-day schedule?
Question 68 Within what time must an inspection report be completed under the EPA CGP?
Question 69 Which area must be inspected?
Question 70 Areas of the site have completed stabilization. How may inspection frequency change there?
Question 71 If you inspect on the 14-day schedule, how do you show a storm triggered an inspection?
Question 72 A discharge is happening during the inspection. What must the inspector do?
Question 73 A silt fence needs sediment removed but is otherwise intact. What is this?
Question 74 A section of silt fence was never installed where the SWPPP shows it. What does the CGP require?
Question 75 A corrective action doesn't need a new control or significant repair. What is the deadline?
Question 76 A blown-out sediment basin outlet needs significant repair. What is the deadline?
Question 77 When must a corrective action condition be entered in the log?
Question 78 Under the EPA CGP, when must stabilization be initiated on an area that will be inactive for 14 or more days?
Question 79 A site has 8 acres disturbed at once. How long does it have to complete stabilization after initiating it?
Question 80 What vegetative cover meets final stabilization under the EPA CGP?
Question 81 How does adding impervious surface typically change runoff?
Question 82 What is the main purpose of a dry detention pond?
Question 83 What distinguishes a retention (wet) pond from a detention pond?
Question 84 Which practice primarily reduces runoff volume?
Question 85 What is low impact development (LID)?
Question 86 Which MS4 control measure addresses permanent stormwater management for new development?
Question 87 What is the most common reason permanent stormwater practices fail?
Question 88 Which practice uses a stone reservoir under a surface that lets water pass through?
Question 89 What does MS4 stand for?
Question 90 How many minimum control measures do small MS4 permits require?
Question 91 Which is one of the six minimum control measures?
Question 92 The construction site runoff control measure applies to sites disturbing at least how much land?
Question 93 Which permit does EPA issue for industrial stormwater where it's the permitting authority?
Question 94 What is a no exposure certification?
Question 95 Which routine requirement is common under industrial stormwater permits?
Question 96 Why do cities review construction erosion control plans?

Last reviewed: October 25, 2026 · Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.