BEYOND CONSTRUCTION: MS4 AND INDUSTRIAL STORMWATER PERMITS (FREE LESSON 12 OF 12)
stormwaterplanning.us/free-training/ms4-and-industrial-stormwater/

type        free mini-training lesson with 8-question quiz (graded in-browser, nothing saved)
time        13 minutes
summary     Free lesson on the other NPDES stormwater programs: MS4 Phase I and II, the six minimum control measures, industrial stormwater permits and the MSGP, sectors, inspections and no exposure certification. 8-question quiz.

objectives
- Explain what an MS4 is and who needs MS4 permit coverage
- List the six minimum control measures for small MS4s
- Describe how industrial facilities are permitted for stormwater
- Connect MS4 and industrial programs to construction projects

sections
- Municipal separate storm sewer systems (MS4s)
- The six minimum control measures
- Industrial stormwater
- How the programs connect
- Key takeaways

standards   40 CFR 122.26 and 122.34; EPA Multi-Sector General Permit

certificate course  https://stormwaterplanning.us/qualified-swppp-preparer-training/
note        Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

Courses delivered by HAZWOPER OSHA Training, LLC, an IACET Accredited ProviderDelivered by an IACET Accredited Provider

Leer en espaƱol

Free Mini-Training · Lesson 12 of 12

Beyond Construction: MS4 and Industrial Stormwater Permits

Construction is one of three NPDES stormwater programs. Learn how municipal (MS4) and industrial stormwater permits work, and how they connect to construction sites.

  • 13 min
  • 8-question quiz
  • Intermediate
  • Free · no sign-up
On this page
  1. What you'll learn
  2. Municipal separate storm sewer systems (MS4s)
  3. The six minimum control measures
  4. Industrial stormwater
  5. How the programs connect
  6. Key takeaways
  7. Lesson quiz

In this lesson

What you'll learn

  • Explain what an MS4 is and who needs MS4 permit coverage
  • List the six minimum control measures for small MS4s
  • Describe how industrial facilities are permitted for stormwater
  • Connect MS4 and industrial programs to construction projects

Municipal separate storm sewer systems (MS4s)

An MS4 is a publicly owned conveyance or system of conveyances (roads with drainage, catch basins, curbs, gutters, ditches, pipes and storm drains) that discharges to waters of the U.S. and isn't part of a combined sewer or a sewage treatment plant. MS4 operators include cities, counties, state DOTs, universities, military bases, hospitals and prisons.

  • Phase I (1990) covered medium and large MS4s, generally serving populations of 100,000 or more, under individual permits.
  • Phase II (1999) added small MS4s in urbanized areas, usually under general permits.

The six minimum control measures

Small MS4 permits require a stormwater management program built on six minimum control measures (40 CFR 122.34):

  1. Public education and outreach on stormwater impacts.
  2. Public involvement and participation in developing the program.
  3. Illicit discharge detection and elimination (IDDE): mapping the system, finding and stopping non-stormwater discharges such as illegal hookups and dumping, and outfall screening.
  4. Construction site stormwater runoff control: an ordinance, plan review, inspections and enforcement for construction sites disturbing one acre or more.
  5. Post-construction stormwater management in new development and redevelopment: permanent controls and long-term maintenance. See lesson 11.
  6. Pollution prevention and good housekeeping for municipal operations, such as street sweeping, maintenance yards and staff training.

Industrial stormwater

Facilities in listed industrial categories need NPDES coverage for stormwater from industrial activity. EPA issues the Multi-Sector General Permit (MSGP) where it's the permitting authority, and authorized states issue their own industrial general permits. The MSGP groups facilities into sectors identified by letter, such as scrap and waste recycling, vehicle and equipment maintenance at transportation facilities, and many manufacturing types.

Typical industrial permit requirements:

  • An industrial SWPPP describing the facility, potential pollutant sources and control measures.
  • Control measures such as good housekeeping, minimizing exposure, preventive maintenance, spill prevention and erosion control.
  • Routine facility inspections and quarterly visual assessments of stormwater discharges.
  • Monitoring for some sectors, such as benchmark and effluent limit sampling, and corrective actions when needed.

Facilities whose industrial materials and activities are not exposed to stormwater may qualify for the no exposure certification exclusion (40 CFR 122.26(g)).

How the programs connect

  • Construction site runoff enters the MS4, so the city's construction program regulates your site alongside the construction general permit.
  • Industrial facilities under construction or expansion may need construction coverage too.
  • Illicit discharge programs catch prohibited construction discharges, such as concrete washout in a storm drain.

Key takeaways

  • MS4s are publicly owned storm sewer systems. Phase I covered medium and large systems; Phase II added small urbanized MS4s.
  • The six minimum measures: education, involvement, IDDE, construction runoff control, post-construction management and municipal good housekeeping.
  • Industrial facilities get coverage under the MSGP or a state industrial permit, with SWPPPs, inspections, visual assessments and monitoring.
  • No exposure certification can exclude facilities with no exposure of industrial activity to stormwater.

Knowledge check

Lesson 12 quiz: 8 questions

Choose one answer for each question, then select Check my answers. Score 80% or higher to pass. Your answers stay in your browser and are never saved.

Question 1 What does MS4 stand for?
Question 2 How many minimum control measures do small MS4 permits require?
Question 3 Which is one of the six minimum control measures?
Question 4 The construction site runoff control measure applies to sites disturbing at least how much land?
Question 5 Which permit does EPA issue for industrial stormwater where it's the permitting authority?
Question 6 What is a no exposure certification?
Question 7 Which routine requirement is common under industrial stormwater permits?
Question 8 Why do cities review construction erosion control plans?

Sources and official references

Last reviewed: October 25, 2026 · Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.