Under Part 2.2.12 of the EPA Construction General Permit, a sediment basin or similar impoundment must provide storage for either the calculated runoff volume from a 2-year, 24-hour storm, or 3,600 cubic feet per acre drained.
Other EPA CGP basin requirements
- Locate the basin outside receiving waters and natural buffers.
- Design it to avoid collecting water from wetlands.
- Use outlet structures that withdraw water from the surface (such as a skimmer or floating riser), unless infeasible.
- Use erosion controls and velocity dissipation at inlets and outlets.
- Maintain it to keep its sediment storage capacity.
Sediment trap or basin?
Many state manuals use sediment traps for small drainage areas and sediment basins for larger ones, with engineered outlets and embankments. Thresholds vary by state, so follow your state's BMP manual and permit, which may require more storage than the federal minimum.
Learn the full set of sediment controls in the free sediment control lesson.
Sources and official references
Last reviewed: October 25, 2026 · Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.