CONCRETE WASHOUT: REQUIREMENTS, SETUP OPTIONS AND MAINTENANCE (FREE GUIDE)
stormwaterplanning.us/guides/concrete-washout/

summary     Why concrete washout water is a stormwater pollutant, EPA Construction General Permit washout requirements, prefabricated vs. lined pit washouts, sizing, signage, maintenance and disposal.

sections
- What the EPA Construction General Permit requires
- Washout options
- Setup tips
- Maintenance and disposal

faq
Q: Why is concrete washout water a problem?
A: It's highly alkaline (high pH) and full of fine cement particles that can harm fish and other aquatic life and contaminate soil and groundwater if it reaches storm drains, waters or the ground.
Q: What are the EPA requirements for concrete washout?
A: Under the 2022 EPA Construction General Permit, wash water must go into a leak-proof container or lined pit sized to prevent overflows, liquid wastes can't be discharged to drains, waters or the ground, hardened concrete is disposed of with construction waste, and washouts are located as far as possible from waters, drainage features and inlets.
Q: How often should a concrete washout be emptied?
A: Before it can overflow. Many contractors pump or replace washouts when they reach about two-thirds to three-quarters full, and keep extra capacity before forecast rain.

note        Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

Courses delivered by HAZWOPER OSHA Training, LLC, an IACET Accredited ProviderDelivered by an IACET Accredited Provider

Free Guide

Concrete Washout: Requirements, Setup Options and Maintenance

Concrete washout water is one of the most common prohibited discharges on construction sites. Here is what the EPA permit requires and how to set up a washout drivers actually use.

  • 6 min read
  • Updated October 25, 2026
On this page
  1. What the EPA Construction General Permit requires
  2. Washout options
  3. Setup tips
  4. Maintenance and disposal
  5. FAQ

When ready-mix trucks, pumps, chutes and tools are rinsed, the water carries cement fines and is highly alkaline (high pH). Washed into a storm drain or onto the ground, it can harm aquatic life and contaminate soil and groundwater.

What the EPA Construction General Permit requires

Under EPA's 2022 CGP, wastewater from concrete washout is a prohibited discharge unless managed by an appropriate control, and wastewater from washing out stucco, paint, form release oils, curing compounds and other materials is prohibited. For washing applicators and containers of these materials, the permit requires operators to:

  • Direct wash water into a leak-proof container or a leak-proof, lined pit designed so no overflows occur from inadequate sizing or rain.
  • Not dump liquid wastes into drainage features, storm inlets or receiving waters, and not dispose of them on the ground or by infiltration. Follow state, tribal and local disposal rules.
  • Remove and dispose of hardened concrete with other construction waste.
  • Locate washout activities as far away as possible from receiving waters, drainage features and storm drain inlets, and use designated areas.

State permits have similar or stricter rules.

Washout options

OptionHow it worksNotes
Prefabricated washout containersRented steel or plastic bins delivered and serviced by a vendorLeak-proof by design; vendor pumps and hauls
Lined pitExcavated or bermed area lined with heavy plastic sheeting without seams or tearsMust be sized and maintained; liner punctures are common
Above-ground lined structureStraw bales or lumber frame lined with plasticQuick to build; check liner and walls often
Truck-mounted / chute washout systemsCollect washout at the truck for return to the plantReduces on-site washout volume

Setup tips

  • Size for the expected number of trucks and pours, plus rain.
  • Place it near the pour but away from inlets, ditches and waters, on level ground.
  • Post a "Concrete Washout" sign and tell drivers and pump operators where it is.
  • Protect it from traffic damage and keep the liner free of tears.

Maintenance and disposal

  • Inspect at every SWPPP inspection and during pours.
  • Don't let it fill to overflow. Many contractors pump or replace it when it reaches about two-thirds to three-quarters full, before rain does the rest.
  • Let water evaporate or have it pumped and hauled per local rules; break up and dispose of hardened concrete with construction waste.
  • Replace damaged liners immediately.

See all pollution prevention practices in lesson 7.

Sources and official references

Last reviewed: October 25, 2026 · Free general education based on the Clean Water Act, EPA NPDES rules and the EPA Construction General Permit. Your governing permit (EPA, state, tribal or local) controls. This is not legal advice, not EPA-approved, and not a California QSP/QSD or other state credential, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

FAQ

Frequently asked questions

It's highly alkaline (high pH) and full of fine cement particles that can harm fish and other aquatic life and contaminate soil and groundwater if it reaches storm drains, waters or the ground.

Under the 2022 EPA Construction General Permit, wash water must go into a leak-proof container or lined pit sized to prevent overflows, liquid wastes can't be discharged to drains, waters or the ground, hardened concrete is disposed of with construction waste, and washouts are located as far as possible from waters, drainage features and inlets.

Before it can overflow. Many contractors pump or replace washouts when they reach about two-thirds to three-quarters full, and keep extra capacity before forecast rain.